Llandinam Windfarm Repowering

Llandinam Windfarm, formerly known as Penrhyddlan and Llidiartywaun, is one of the oldest within the ScottishPower Renewables portfolio. It is operated with Eurus Energy under the trading name of CeltPower Ltd.

In May 2008, we submitted an application to repower Llandinam Windfarm. 

In January 2012, we submitted Supplementary Environmental Information to present the findings of additional survey work and changes made in response to stakeholder comments which entailed the removal of three turbines.

In April 2013, we submitted further Supplementary Environmental Information removing a further five turbines in response to consultation feedback.

On 7th September 2015 the project received consent under Section 36 of the Electricity Act 1989 from the Secretary of State for Energy.

In June 2019 we submitted a Section 36C planning application to the Secretary of State for Business, Energy and Industrial Strategy to apply for a variation to the Section 36 consent for the repowering of the Llandinam Windfarm, Powys, Mid Wales.  The Variation Application seeks to amend the Section 36 repowering consent that was granted on 7 September 2015 by requesting an extension to the implementation timescale for the Development for a further 5 years

The project team can be contacted directly by llandinamwindfarm@scottishpower.com